School Board Meeting - September 11, 2012
Watch on YouTube →
Overview
Falls Church City Public Schools conducted a September 11, 2012 school board meeting that combined statutory compliance items, consent agenda personnel actions, and multiple policy/finance decisions with major facilities and technology initiatives. Key items included approving the Hess Construction contract modification to add Thomas Jefferson Elementary School Task 2 (scope for sprinkling, fire alarm, ceilings/lighting, roof, windows, HVAC, electrical service, media center, intercom, and lower level renovations) using a 65% design/guaranteed maximum pricing structure and a $340,000 design allowance plus $58,880 structural engineering allowance; supporting baseball/softball field lighting fundraising through CIP plus community contributions and an IRS fiscal sponsorship mechanism; and adopting second readings for multiple policies (including a detailed tutoring policy framework with on-campus approval/liability coverage requirements) plus adopting the Code of Civility and Organizational Protocol. The meeting also advanced FY12 fund balance reporting and approved a FY13 operating budget amendment to increase technology spending by $500,000, while outlining FY planning steps such as Board policy review scheduling and the next steps for a school board vacancy interview on October 2, 2012.
Key takeaways
- Thomas Jefferson Elementary School Task 2 was structured around a 65% design milestone with Hess Construction to reduce upfront risk: the board commits to $340,000 for design through 65% plus $58,880 for structural engineering allowance, then evaluates remaining scope at guaranteed maximum pricing.
- Public safety improvements were operationally tied to facility work: cameras and emergency repairs (baseball backstop, tennis courts, MEH entrance gate) and an internal safety/security restructure plus a children’s safety officer role support both construction safety and daily student movement monitoring.
- Baseball/softball lighting funding used a hybrid public-private approach: $110,000 CIP + community contributions (~$60,000) and a planned ~$190,000 gap bridged via IRS-approved fiscal sponsorship so cash arrives up front while signage/ad revenue develops over time.
- Policy 8.57 tutoring was expanded to permit several tutoring scenarios on school grounds but tightened with required building principal approval and liability coverage requirements (general liability and sexual abuse/molestation coverage), plus careful attention to facility fee waiver discretion.
- Falls Church City Public Schools advanced technology spending through budget action: FY13 operating budget amendment increased revenues and expenditures by $500,000 to accelerate technology procurement with purchase orders and shipping planned immediately.
Chapters
- Falls Church City Public School Board certifies closed-session compliance with Virginia law under the Virginia Freedom of Information Act, including Virginia Code §2.2-3711(B).
- Board members conduct a roll call vote confirming only lawfully exempt public business matters were discussed and only those identified in the motion were considered.
- Board Chair requests a moment of silence for the September 11 anniversary.
- Agenda amendment switches item 8.04 to item 8.02 related to baseball lights and other project updates; agenda is moved and seconded.
- Brian Rye submits a letter raising concerns about technology being treated as a panacea for education and includes a New York Times article.
- Annual school safety reporting covers facility safety upgrades: additional cameras, emergency repairs, baseball backstop repairs scheduled within 1 to 2 weeks, tennis court repairs starting, and repairs to the MEH entrance gate off Route 7.
- Safety/security responsibilities are restructured so SEVI facilities connect safety and security more directly to principals.
- A children’s safety officer role is created by moving staff from George Mason to Thomas Jefferson (TJ), supporting construction-zone boundaries and daily playground monitoring.
- Board approves reappointment for Steve Papillion (part-time science teacher, George Mason) for 2012 to 2013.
- Multiple 2012 to 2013 appointment approvals include system-wide paraprofessionals (Tiffany Velishka, Thiel Velishka, Jessica Sadek, Carolyn Woods), transportation (Kathy Finney), and teachers across George Mason and Mary Ellen Henderson.
- Resignation accepted: Megan Atkinson (PE teacher, Mary Ellen Henderson Middle School) effective immediately; extra pay/EPE assignments approved for instructional leadership (GT advisory, EPD) and extracurricular/athletic duties.
- Board approves annual filing for school-affiliated organizations: Foster’s Education Foundation, Foster’s Elementary PTA, Mary Ellen Henderson Middle School PTA, and George Mason High School PTSA.
- VSBA delegates approved: Mr. Kieran Sharp as VSBA Delegate and Ms. Charlotte Highland as VSBA Alternate Delegate for 2012 to 2013.
- Board approves first amendment to Superintendent Dr. Tony Jones’ contract.
- Board accepts independent auditor’s report for Falls Church City Public School activity funds for FY ending June 30, 2012.
- Change order proposes adding Thomas Jefferson Elementary School Task 2 to Hess Construction’s comprehensive agreement with a construction cost limit of $4,000,000.
- Procurement approach: Hess advances design to 65% documents, submits a guaranteed maximum price at 65%, then design/cost negotiations continue toward 100%.
- Task 2 includes: sprinkling of existing building, new fire alarm system, all-new ceilings, and new light fixtures.
- Major envelope/MEP items include: complete roof replacement, aluminum windows/storefronts, foundation/water seepage correction, and a complete new HVAC system (including ductwork replacement).
- Technology/interior changes include: media center renovation and expansion with entrance reconfiguration, new intercom system (master station plus addition tie-ins), classroom/carpet updates, intercom connectivity, painting/classroom/quarter walls, operable partition replacement, and lower level renovations (expanded music room, expanded art room ~1,200 sq ft with kiln, multiple classrooms, daycare office, and added storage).
- Board discusses why early approval is needed to cross contracting thresholds while assessment and critical-item selection continue over coming months.
- Schedule constraints: Task 1 finishes end of April; Task 2 targeted for completion by August to avoid ceiling/light work during school occupancy.
- Process addresses uncertainty and cost risk: ceiling/roof/HVAC/windows items require architectural/engineering documentation to avoid inflated contingencies.
- Motion: modify Hess Construction contract to include Task 2 for Thomas Jefferson Elementary.
- Seconded and passed unanimously (aye votes recorded), enabling design work at 65% and further evaluation before committing to additional scope at 65% pricing.
- Project recap estimates baseball/softball lights at ~$360,000; CIP allocation is $110,000 leaving an ~$250,000 gap.
- Community contributions bring ~$60,000; remaining gap (~$190,000) is planned via boosters fundraising using allowable advertising/signage/naming rights under board policy.
- Outside counsel retained to ensure IRS compliance for a fiscal sponsorship approach.
- Individuals provide cash upfront through boosters; as ad revenue is earned over time, revenue repays/“passes through” funds to the arrangement so the board can contract the project once cash is secured.
- Board member asks about Parks and Recreation Department involvement; director Danny Schlint is described as involved informally since early discussions with anticipated support for expanded night leagues and youth program access to lit outfields.
- TJ Task 1 progress: water line coordination with the city to avoid sinkholes while fixing parking lot grade; joint effort using HESS.
- Tennis courts: shared-cost effort with city coordination via Recreation Advisory Board endorsement (amount not yet determined).
- Cherry Street: initial assessment plan moved earlier by contract timing; possible vacancy date shifts from Dec 2013 to July 1, prompting readiness and accelerated planning.
- Policy 4.11 updated to reflect Virginia code change allowing notification to parents in ways other than written format while still computing and distributing per-pupil cost.
- Policy 4.23 purchasing thresholds updated per Virginia Public Procurement Act changes, including professional services thresholds and competitive bidding/negotiation triggers.
- Board and counsel discuss harmonizing terminology using VSBA model language: keep “tenured” term of art for instructional personnel and align the other reference to remove “continuing contract status” phrasing.
- Agreement is reached to insert “tenured” and remove additional “continuing contract status” language for consistency.
- Policy 8.38 clarifies participation in the system is a requirement rather than discretionary “may.”
- Policy 8.57 expands tutoring allowance details, clarifying FCCPS can pay staff to tutor students and addressing elective/private tutoring on campus with principal approval and explicit liability coverage requirements.
- Tutoring framework organized into cases: building-principal-directed tutoring, FCCPS-paid tutoring with best-resource teachers, and student/family-initiated tutoring to occur on campus.
- Board requests policy clarity that paid-compensated tutoring must take place on school grounds and be approved by the building principal.
- Discussion includes facility rental fee waivers and discretion; approach described as giving flexibility to waive fees when tutoring FCCPS students while maintaining liability coverage and facility-use procedures.
- Student records policy 9.8 adjusts definitions to match federal statute/regulations and retains date of birth as “directory information” for athletic eligibility requirements.
- Medicines policy 9.38 updates include epinephrine availability without known allergies and uses a standing order; Dr. Gordon Thies is publicly thanked for enabling implementation logistics, training, protocols, and delivery rules.
- Board questions whether providing required information about the Attorney General mandate has an enforcement “stick” (potential funding consequences).
- Action: item is set aside; counsel is asked to submit to governor’s task force on local mandates for removal of “unnecessary, outdated” requirements.
- Mr. Horn presents legal resources and flowchart showing when superintendent accesses counsel first and when the board chair/board proceeds next.
- Board member asks whether paths are parallel or sequential; described as superintendent reaching out early to appropriate counsel (e.g., Reed Smith for special education issues, city attorney channels for personnel issues) while ensuring options for separate firms when beneficial.
- Policy review schedule targets sections 2, 3, 5, 8, and 9 older than 2008, projecting ~25 policies for 2012 to 2013, with future years focusing on older categories and statutory changes.
- Green building/LEED lead policy: city requested consideration, but board intent is that LEED requirements depend on CIP funding; Cherry Street renovation may make full LEED certification costly (e.g., potential ~25% recommendation).
- Board adopts Code of Civility and Organizational Protocol including press communication norms (chair/vice chair) and meeting norms including the hard-stop target of 10 p.m. (not always followed).
- Protocol reiterates staff protection: no single board member can instruct staff directly; requests route through Superintendent and board majority for major tasks.
- Work plan is a joint board/superintendent effort; performance evaluation tied to accomplishments against the plan.
- Work plan organized around five pillars: small schools/small classes/outstanding staff; readiness for learning; and 21st-century teaching and learning; discussion includes ensuring GT plan items are captured system-wide.
- Dr. Tony Jones delays full academic progress sharing because subgroup data required for Virginia AMOs was not yet available after September 5 state publication.
- Hand-calculation suggests subgroup results around or near state average in math and overall; board will receive corrected data next month to avoid error.
- FY12 ending balances (unaudited estimate as of September 7): operating fund drops from ~$2.861M start to ~$2.335M at June 30; $1.45M assigned to support FY13 budget and ~$885K planned for FY14.
- Board approves amendment increasing FY13 operating budget revenues and expenditures by $500,000 with amended total of $38,207,400 and amended city appropriation of $29,975,200, described as equipment shipping and placed in students’ hands shortly.
- Board requests explanation of city’s assumed 2% revenue growth forecasting methodology used in financial projections and asks for updated/in-context rationale for multi-year budgeting.
- Commitment for financial status update later in October after audited results and first tax collections are available.
- Celebrations: theater department wins American Prize in Musical Theater and American Prize in Conducting; fall sports begin.
- District highlights: updated FCCPS.org website with video/social features; run for the schools weekend noted with donation counts; class size management described with specific building constraints (e.g., TJ around 22 to 23, second grade no room, George Mason biggest PE scheduling challenge due to gym limits).
- Board member Rasnick links compensation strategy to achieving top talent and pushes for faster movement toward being the top-compensating system in the area (Yankees analogy).
- Board member offers critique of Virginia’s waiver approach under No Child Left Behind flexibility, arguing for “world-class” expectations for all students including low-income and minority groups.
- Six applicants submit qualifications to fill Rosara Garberi’s seat; special meeting set for October 2, 2012 at 7:00 p.m. for candidate question-and-deliberation process to select replacement until December 31, 2013.
- Minutes approved for August 14, 2012 and August 27, 2012; one board member abstains; meeting adjourned after final procedural motions.